| |
| 
Project
newsletters
and information regarding current projects:

City of Grand Junction 2010 CIP
City of Grand Junction
2010 Transportation Projects |
As of March 2010 |
- HMA Overlay Contract – suspended for 2010
- Bridge Replacements
- Canal Bridge on 26.5 Rd @ F.6
- Bridge on D Rd over No Thoroughfare Wash
- Interchange Construction
- 29 Rd I-70B Interchange construction June through Nov 2011
- Intersection Improvements
- 23 Rd & G Rd Roundabout (900 cu.yd. concrete pavement; 415’ of 60” R.C.P.)
- Street Improvements
- Main St Renovation from 1st St to 4th St ( complete June, 2010)
- Main St Renovation from 4st St to 7th St (bids September 2010) (construction January – June, 2011)
- Alley Reconstruction
- (1,640 sq. yd. of 8” concrete pavement)
- 11th St to 12th St between North Ave & Belford Ave (includes 470’ of sewer line replacement)
- 3rd St to 4th St between Colorado Ave & Ute Ave (sewer replaced in 2009)
|
 |
2010 Utility Projects |
- Water Line Replacements (State Revolving Funds)
- Phase 1 (2,050’ of 6” PVC, 2,160’ of 8” PVC; 8,380’ of 12” PVC; 95’ of 18” PVC)
(construction March – July, 2010 by MA Concrete)
- North Ave from 1st St to 15th St
- Orchard Ave from 7th St to Cannell Ave
- 8th St from Hall Ave to Orchard Ave
- Hall Ave from 8th St to Cannell Ave
- Cannel Ave from North Ave to Orchard Ave
- Phase 2 (1,300’ of 6” PVC; 6,780’ of 8” PVC; 60’ of 10” PVC)(construction March– July, 2010 by Schmidt Earth Builders)
- Patterson Rd from 7th St to 27 1/2 Rd
- 15th St from Elm Ave to Bookcliff Ct
- Phase 3 (3,500’ of 6” PVC; 7,500’ of 8” PVC) (advertise 3/21 - open bids 4/6) (construction April 26– August, 2010)
- North Ave from 28 Rd to 29 Rd
- 27 1/2 Rd from Sunshine Ln to Unaweep Ave
- Kennedy Ave from 25th St to 28th St
- 18th St from North Ave to Bunting Ave
- 28 1/2 Rd from North Ave to Elm Ave
- College Place from North Ave to Texas
- Texas from College Place to 12th St
- Elm Ave from Cannel to Houston
- Houston – North Ave to Bunting Ave
- Bunting from Cannel to Houston
|
- Sanitary Sewer Projects (Build America Bonds)
- New Interceptor Sewer Line from 15th & Winters south to Riverside Parkway, then west along the south side of the Parkway to 5th & Struthers (5,627’ of 24” PVC; 204’ of 21” CIPP; 155’ of 27” CIPP; 122’ of 36” jacked steel casing) (construction March – July, 2010 by MA Concrete)
- Easter Hill LID (1055’ of 6” and 8” PVC (construction April– May, 2010)
- Persigo Wash Siphon & RR Interceptor Rehab from Persigo Wash to Persigo Wastewater Treatment Plant(1,700 ‘ of 54” CIPP)
- Fruitvale Sanitation District Outfall Replacement (5,000 of 24” PVC) (open bids September 2010/ construction October – January 2011)
- Sewer Rehabilitations
- Patterson Road from 25 ½ to 26 ½ Rd (4900 LF of 15” and 18” CIPP) Advertise August / construction Fall 2010.
|
 |
City Engineers have used growth projections
for the next 20 years to prioritize and design the streets
we need to continue to grow gracefully. These projects
will focus on keeping our traffic flowing smoothly, widening
of streets, replacement of outdated utilities, and the
creation of new roads and intersections. |
| Funding projects: |
| The citizens of Grand Junction are fortunate
to have a source of revenue that allows the City to stay
committed to improving and maintaining capital projects without
going into debt. In 1987, the Grand Junction City Council
adopted an ordinance that increased the sales tax rate by ¾ of
one percent. The tax increase, which was supported by voters,
raised the total City sales tax to 2 ¾ percent, and was instituted
for the specific purpose of funding economic development
and general capital improvement projects. |
| Making Traffic Projections |
Traffic modeling is an important tool
that helps us to understand the potential impacts of traffic
over time. It provides engineers with a way of evaluating
certain actions, such as increasing traffic on the street
system. Special computer programs are used to estimate
trips between key traffic analysis zones. Because of these models and projections,
we see a real need to improve our streets and intersections
before traffic becomes too congested. |
| How do we prioritize projects? |
Public Works and Planning Projects
(funded by our ¾ percent Capital Improvement Program) are
annually reviewed and prioritized during budget review.
During this time, we must decide which projects will take
precedent. To help us decide, we look at the following
criteria:
- Planning for future growth by using
our Growth Plans, adopted zoning, and long- range
transportation studies.
- Citizen requests for improvements.
- Existing or future needs for additional
traffic.
- Needs for safety improvements and
elimination of hazards. Accident history and substandard
facilities help us to determine these needs.
We also take into account the costs of
these projects, the availability of grants and outside
funding sources are considered. |
| Why does it take so long to get a project
done? |
| Once a project is funded and scheduled,
project development must be completed. This process can take
several months or several years, depending on the type of
project. A typical street improvement project will require
two years of preparation work before construction begins.
Following is an outline of the usual project development
process. |
| First Year: Project Development |
- A citizen participation program is developed
to involve property owners, utility companies and others
who may be affected by the project.
- Surveys and topographic maps of the
project area are prepared.
- Rights-of-way, easements and ownership
of properties in the vicinity are researched.
- Preliminary design studies, including
development and analysis of alternatives.
- Geo-technical studies, including groundwater
and soil investigations are completed.
- Recommendations for final design are
formulated and presented to citizens, the City Council
and other authorities, based on the results of preliminary
design studies.
- Final design is selected, and detailed
construction drawings and specifications are completed.
|
| Second Year: Project Development |
- Negotiations and legal processes for
acquisition of rights-of-way and easements are conducted.
- Relocation of utilities are planned,
scheduled and coordinated with utility companies.
- Public participation programs are continued,
informing anyone who may be interested in or affected by
the project.
|
| Third Year: Project Construction |
- Final revisions are made to construction
drawings and bid documents.
- The project is advertised for bidding
by pre-qualified contractors.
- Bids are opened and evaluated. A recommendation
is made for the award of the construction contract.
- City Council awards the construction
contract.
- Construction begins. City Engineers
perform quality assurance inspection and material testing
for all phases of construction.
|
| Right-of-Way Acquisition |
When streets are expanded, the City must acquire
the right-of-way along each side of the existing road. With fairness
as a top priority, the City's goal is to assure fair and equal
treatment for all affected property owners. The right-of-way acquisition process typically
follows these nine steps:
- Decide
exactly what parts of the right-of-way must be purchased.
- Research titles,
so they know exactly who owns affected property.
- Prepare right-of-way
plat maps.
- Representatives meet with property
owners to explain where, why, and how much of an owner's property
is required.
- Land is appraised to determine the fair
market value of the land and any improvements which may be
lost.
- Prepares a "Determination
of Compensation," which summarized the fair market value
of the required property.
- A City representative presents a formal offer to purchase the required land.
- Property owners and City representative work together
to resolve any problems which may arise.
- The property is purchased.
The City's right-of-way acquisition policies
reflect the City's need to continue to protect health, safety
and welfare of citizens, while at the same time protecting the
rights of individual property owners.
|
|
| |
|
|
|

Storm Drainage
In recent years, we've seen the need for a
plan to deal with excess water created by storms. Two projects addressing our storm drainage master plan are design
and construction of storm water detention basins to reduce peak
storm flows and flooding along the Independent Ranchman's Ditch
and Leach Creek.
How do we prepare the budgets?
Project budgets for Public Works and Planning
are based on cost estimates for:
- Project administration (6 to 15 percent
of the construction cost)
- Engineering
- Right-of-way acquisition (based on sales
of similar properties, includes compensation for fair market
value of the land, easements, landscaping, and structures.)
Also included are expenses for researching properties, preparing
legal descriptions, title services and closing costs.
- Construction (using bid prices from similar
projects)
Cost estimates for future years are increased
by 4 percent per year from the present value to account for inflation.
This page updated
Tuesday, August 10, 2010
|
|
|