Search

Station 6 updates


To receive updates on the project:

Text GJFD6 to 888777
Or visit us on social media:  
GJFD twitter link


Update Weeks of July 27th-August 9th:

The week of August 3rd street improvements will begin, with some lane narrowing and delays possible along 27 Road. The living quarters of the station are currently having brick exterior installed, while in the apparatus bay structural steel work is happening to prepare for the roof.

 

July 27th-August 2nd

  • Interior utility work continues
  • Exterior brickwork continues
  • Structural steel work in the bays
  • Steel stairs installed in tower

 

August 3rd-9th

  • Street improvements begin along 27 Road, some delays expected
  • Interior utility work continues
  • Exterior brickwork and siding continues
  • Exterior siding for the bay area begins

August 10th-6th

  • Street improvements continue along 27 Road, some delays expected
  • Exterior brickwork and siding continues
  • Interior utility work continues
  • Interior insulation installed

August 17th-23rd

  • Street improvements continue along 27 Road, some delays expected
  • Exterior brickwork and siding continues
  • Interior drywall work begins
  • Slab preparation for apparatus bays
  • Bay and tower roof work begins

August 24th-30th

  • Exterior concrete work begins
  • Drywall work continues
  • Roof work continues
  • Concrete slab poured in apparatus bays

 

For Questions or Concerns:

Matt Carson 
Battalion Chief
(970)549-5871
mattc@gjcity.org


July 27th


July 21st

July 7th

June 30th

June 24th


June 9th