Search

Station 6 updates


To recieve updates on the project:

Text GJFD6 to 888777
Or visit us on social media:  
    GJFD twitter link  


Update Week of May 18-24:

This week at GJFD Station 6, construction crews will be focusing on utilities; placing water, electric, and sewer connections in the building. With soils that hold lots of moisture, crews installed special protection and drainage to preserve the foundation of the station, and will finish backfilling and covering that work this week. Lastly, concrete slabs for part of the station will be poured this week. Construction continues to move forward with minimal impacts to the neighborhood. Construction crews will not be working on Monday, May 25th in recognition of Memorial Day. 

May 17th-23rd

  • Complete foundation backfill
  • Place utility starts for plumbing, electric, sewer
  • Pour concrete slab for part of the station

May 24th-30th

  • Memorial Day Holiday: No construction
  • Begin masonry work

May 31st-June 6th

  • Continue masonry work
  • Begin wood framing

June 7th-13th

  • Continue masonry work
  • Begin wood framing

 

For Questions or Concerns:

Matt Carson 
Battalion Chief
(970)549-5871
MattC@GJCity.org


May 19th, 2020

April 2nd, 2020

May 1st, 2020