The G Road bridge is scheduled to be completed by the end of early August 2022. The City has worked with its contractor and Xcel Energy to develop an updated timeline that will reflect Xcel's relocation of two gas lines. This additional work means the project will be completed at the beginning of August instead of the end of June as originally planned.
The new G Road bridge location is shifted east approximately 75 feet from the previous G Road bridge to accommodate a pedestrian underpass. This underpass will connect Canyon View Park with a future trail extension project that will be located on the south side of G Road.
Utility relocations (sewer, water, storm, gas, electric, and communications) are included with this project and are necessary for new bridge construction and the previous bridge demolition.
More information can be found on the City’s 24 Road & G Road Projects webpage.