2022 Asphalt Overlay Project

Due to unforeseen circumstances, 21 ½ Road and 25 1/2 Road were not completed last week but are scheduled to be paved this week

21 ½ Road between Hwy 6 & 50 and Storage Court

  • Asphalt paving
  • Expect delays 

25 ½ Road between Independent Avenue and Patterson Road

  • Asphalt milling and paving
  • Expect delays

River Front Trail Improvement Project

  • The River Front Trail will be closed between Bananas Fun Park and the Junior Service League Park/ Redlands Pkwy.
  • City crews are replacing the asphalt trail with concrete 
  • A well-marked detour route will be in place utilizing the bike path alongside Riverside Pkwy.  

City of Grand Junction Leaf Removal Program  

  • Please slow down in areas where crews are working
  • Anticipated Completion – Early December (weather permitting)
  • For more information, visit the city’s website: gjcity.org

Non-City of Grand Junction Projects with Travel Restrictions

North Avenue between 1st Street and I-70B, Resurfacing Project – CDOT

  • This Sunday only Nov. 13, Paving hours will be 10 a.m. to 10 p.m. Alternate route advised, especially east of 28 Road
  • After Sunday the paving operation will continue Monday, Tuesday and maybe Wednesday (2pm until 2am)
  • One lane of traffic in each direction will always be open
  • Be aware of the 20-mph reduced speed limit and 10’ width restriction throughout the work zone
  • Please watch for workers in the “cone zone” and be respectful of their safety
  • Anticipated Completion: Mid December (weather dependent)

CONTACT THE CDOT PROJECT TEAM 

Questions or concerns? Or to be added to CDOT's public outreach contact list to receive construction updates:

23 Road Between H Road and I Road, Utility Construction – Ute Water

  • 23 Road is closed to thru traffic between H Road and I Road
  • Access for residents will be maintained
  • Detour Route will be in place
  • Anticipated Completion – Mid December (weather dependent)

South Camp Road Shoulder Improvement Project – Mesa County

  • Shoulder work along South Camp Road between Monument Road and Rimrock Road
  • South Camp Road may have Intermittent alternating one lane traffic, Monday – Friday, 7 a.m. – 6 p.m. 
  • Expect delays
  • Anticipated Completion – Mid December (weather dependent)

Hwy 141 and Coffman Road (Whitewater), Utility Construction – Private Development

  • Coffman Road closed between Hwy 141 and Gaylord Street
  • Detour route will be in place
  • Anticipated Completion – December 2 (weather dependent)